You are currently browsing the Transition Team Blog weblog archives for the day March 27, 2007.
- Glenmar Road Building Renovations (18)
- New Cut Road (5)
- New Cut Road Building Progress (73)
- Pastors Ponderings (15)
- Phase 2 Info (2)
- Realignment of New Cut Road Progress (7)
- Staff News (3)
- Uncategorized (7)
- November 7, 2008: Staff Trailer
- October 1, 2008: Tough Choices
- September 25, 2008: Changes.
- July 14, 2008: More Photos
- July 14, 2008: Procession Photos
- July 13, 2008: Glorious Day!
- July 9, 2008: Moving Day Ponderings
- June 30, 2008: July 13th is Moving Day!
- June 25, 2008: News From New Cut
- June 21, 2008: God's Schedule, Not Ours
Floor Plans
Other Stuff
Prayer Life
Web Sites
Archive for March 27, 2007
Todays Work
March 27, 2007 by Al Hammer.
The pad where the building sits continues to move forward with the south wall of the lower level getting more walls each day. This picture is more work on the south wall. This is the rebar that is ready for the concrete wall to be poured over it. They will form up the wall tomorrow and pour it on Thursday.

Here is the view from the east looking at the building pad, approximately where the web cam will be viewing from.

This picture is at our first “Progress Meeting” with Oak Contracting’s Project Manager, Bud Woodward, in the foreground, Alexander Design Studio’s Project Architect, Phyllis Cook in the middle and one of the sub contractors in the background.

This is also the first day of BG&E’s work on moving the utilities out of our way so that we can build the acceleration and deceleration lanes on Rt 103 where the “new” New Cut Road intersection will be.

Posted in New Cut Road Building Progress, Realignment of New Cut Road Progress | No Comments »