You are currently browsing the Transition Team Blog weblog archives for the day June 11, 2007.
- Glenmar Road Building Renovations (18)
- New Cut Road (15)
- New Cut Road Building Progress (84)
- Pastors Ponderings (17)
- Phase 2 Info (14)
- Realignment of New Cut Road Progress (9)
- Staff News (4)
- Uncategorized (7)
- October 31, 2009: Looking Good!
- October 16, 2009: Lots of Progress
- September 19, 2009: Starting The Roof
- August 15, 2009: More Walls
- August 7, 2009: Putting In The Walls
- August 1, 2009: Church-Wide Sabbath
- July 28, 2009: More On The Second Floor
- July 19, 2009: Howard County Bond Hearing
- July 11, 2009: 2nd Level Floor Starting
- July 11, 2009: Community Meeting with State Highway Admin
Floor Plans
Other Stuff
Prayer Life
Web Sites
Archive for June 11, 2007
Curb and Gutters
June 11, 2007 by Al Hammer.
The subcontractor is moving quickly on progress with laying curb and gutters on the Montgomery Road improvements along with those along the realigned New Cut Road up to our entrance.
This part of the work should be finished next week.
Posted in Realignment of New Cut Road Progress | No Comments »
Building Blocks
June 11, 2007 by Al Hammer.
I was up at the job site today and the mason had been there and determined the plan of action for starting the masonry walls tomorrow.
With these walls going up and the structural steel within the next week scheduled to start going up, we should begin to seem more definition to the building parameters.
Posted in New Cut Road Building Progress | No Comments »