I know I have been saying that the photos are posted and they haven’t been. Well, here they are!

15 May 2009: Here is a view from “Mount Glen Mar” of the muddy work digging out for the foundation.
Foundation Work

4 June 2009: The concrete pumper is starting to pour some concrete - again it is raining…
Concrete Pumper

13 June 2009: The poured exterior walls are going in. The walls are poured in sections and once they set, the workers move the forms to a new section. Here is the work so far - notice in the background the cinder block walls are also going up.
Walls 1

And here are some of the workers getting the forms ready for the next pour…

Walls 2

Walls 3

2 July 2009: The interior and exterior walls for the lower level are done and the floor has been poured and finished.
Floor 1

Floor 2