Archive for the Glenmar Road Building Renovations Category

News From New Cut

Installation of the metal roofing panels begins today.

Web Cam Problems

On the 10th of February, it was very windy and no big deal, right?  Wrong — it seems the wind literally blew the web cam off the side of the trailer and there it hung until today.  (Ok, I’ve been busy and I should have asked Dale to deal with it, but I was too busy to think of that!)  I mounted it back to the trailer in a slightly different spot that had more than 3/8 plywood to screw to (hopefully) and got the camera aligned.  Unfortunately, while it was hanging by its cable, the camera was rained on and filled about 1/4 of the way with water.  It still works, but the picture has a lot of water vapor messing it up.  Maybe in a few days, the lens area will dry out and the picture will get better (or not).

The good news is that in 3 months to the day, we will be having our Grand Opening celebration!  Thank You God!

Hot August

Today Spirit of Faith started the process of putting in Central Air for the Education Wing.  The A/C compressors were place on the roof top today and they will be working on the ducting in the coming weeks.

Renovations Continue

Spirit of Faith continues to renovate various areas of the current Glen Mar facilities. Today they began renovations of the Youth Hall. It will take them several weeks to remove old and put up new wall board. They are building a closet to house the exposed A/C unit. They are removing all ceiling tile and light fixtures and will replace with new. They plan to put down new ceramic tile on the floor. They are totally remodeling the two bathrooms in the Youth Hall wing.

Last Minute

As Spirit of Faith comes down to the wire with their first event tomorrow, renovations continue.

The main lobby has received new carpet and new lighting. Fluorescent Lights have been removed and more recessed cans have been added along with new ceiling hugger chandeliers. You might also note the new monitor just behind the sanctuary door.

The “104 Lobby” received a new makeover with new furniture and carpet.

The landscaper came Wednesday and has a whole new look for the Front of the Church entrance:

The Fence got a new paint job:

This main entrance received new plantings and a new fence around the BG&E gas equipment.

The lower hallway received a fresh coat of paint:

And the Fellowship Hall is being painted.

New Chair railing and other molding is going up in key places.

Larry and Harry from Glen Mar are working quickly to try to tie into their video system in order to try and assure that we will have visuals on Sunday morning.